Road closed

KENTON ROAD PHASE 5 TO BEGIN MAY 18

Full closure of the Kenton Road and Chestnut Grove Road intersection.
Roundabout proposed improvements image

Kenton Rd. at Central Church Roundabout Starting May 26

Wetland mitigation site construction. Roadside drainage and utility relocations.

KENTON ROAD PHASE 3 COMPLETE

NB Lane from Forrest Avenue to College Road COMPLETE.

April Progress Photos

Questions or Concerns?

Let us know!

Kenton and Central Church Roundabout Timeline

Aerial view of roundabout location.

PHASE 1

5/26/26 - 8/6/26
Wetland mitigation site construction. Roadside drainage and utility relocations.
Aerial of map showing detour for phase 2 construction of roundabout.

PHASE 2

8/6/26 - 9/2/26
Roundabout and roadway construction. Intersection closed to thru traffic. Local access will be maintained for residents.

Construction aerial

Currently in Construction

Phase 4 - Northbound Kenton Road between SR8 and College Road

  • Final roadway configuration from SR 8 to College Road is now in place with temporary striping
  • Final paving
  • Final striping

Phase 5 Kenton Road between Turnberry Drive and Maple Dale Road

  • Crews are currently focused on drainage installation between College Road and Maple Dale Road Looking ahead
  • Construction Phase 5 will require a full closure of Kenton Road at Chestnut Grove Road. A signed detour will be in place to guide motorists safely around the work zone.

CURRENT PROGRESS PHOTOS

Archived Progress Photos